PROGRESS OF WORKS FOR THE MONTH OF
APRIL 2023
Cate-gory | Details of Work | Year of sanction | Anticipated /Sanctioned Cost | Cum. Exp. Up to March 2023 | BG for 2023-24 | Exp. Up to the month/ Cum. Exp. | Physical progress |
NL PB-5 | Hejjala-Chamarajanagar (142 km) (part of Bangalore-Satyamangalam (260 kms) | 1997-98 | 1383 on 50:50 cost sharing basis & land free of cost by GOK for Hejjala to Chamarajanagar | 7.35 | 0.0001(Cap.) | 0.00/ 7.35 | Nil |
Remarks:-
Originally the project was sanctioned between Bangalore - Satyamangalam (260 km). Permission was not granted by Tamilnadu Government as well as CEC to carry out survey in the Satyamangalam Forest Area. Hence project is now being taken up from Hejjala to Chamarajnagar (142 Kms). Land is yet to be given by State Govt.
Project kept under “ABEYANCE” vide Railway Board letter dated 23.10.2019.