PROGRESS OF WORKS FOR THE MONTH OF
DECEMBER 2022
Cate-gory | Details of Work | | Anticipated /Sanctioned Cost | Cum. Exp. Up to March 2022 | BG for 2022-23 | Exp. Up to the month/ Cum. exp | Physical progress |
NL PB-15 | Chikballapur-Gowribidanur (44 km) | | 367.77/0.00 with cost sharing basis & land free of cost by GOK | 0.00 | 0.0001(Cap.)
| 0.00 / 0.00 | Nil |
Remarks;- CCEA clearance awaited. FLS sanctioned separately on 22.07.2022 and tender notice for FLS issued on 23.09.2022. Final Location Survey tender opened on 17.10.22, discharged due to ineligible offers and is being retendered. |