PROGRESS OF WORKS FOR THE MONTH OF
APRIL 2023
Cate-gory | Details of Work | Year of sanction | Anticipated /Sanctioned Cost | Cum. Exp. Up to March 2023 | BG for 2023-24 | Exp. Up to the month/ Cum. Exp. | Physical progress |
NLPB-7 | Bagalkot-Kudachi(142 kms) | 2010-11 | 1654.65/1378 on 50:50 cost sharing basis & land free of cost by GOK | 339.062
| 210Cr.(SF) 150.00Cr(Dep).
| 2.47/ 341.53 | 30% |
The section between Bagalkot - Kajjidhoni (30 Km) was commissioned on 21.06.2018.
For the section between Kajjidoni - Lokapur (7 Km) - Work is in progress and is targeted to be commissioned in the Financial year 2023-24.
Engineering Procurement and Construction (EPC) Tender floated for section between Lokapur - Yadwad (21 Km) on 15.11.2022 for a value of Rs.357.45 Cr and has opened on 20.02.2023. The same is under finalization.
From Yadwad to Kudachi land is yet to be handed over to the Railways from Government of Karnataka. After handing over of 90% of land EPC tenders will be called in stages.