PROGRESS OF WORKS FOR THE MONTH OF
APRIL 2023
Cate-gory | Details of Work | Year of sanction | Anticipated /Sanctioned Cost | Cum. Exp. Up to March 2023 | BG for 2023-24 | Exp. Up to the month/ Cum. exp | Physical progress |
NL PB-17 | Shimoga-Shikaripura-Ranibennur NL (89 km) | 2019-20 | 994.47 50:50 cost sharing basis & land free of cost | 26.78 Cr. | 150 Cr. (Cap.) | 0.29/27.07 | Nil |
Remarks:-
Execution of the project is planned in 2 phases, Shimoga to Shikaripura (46 Km) under phase I and balance Shikaripura – Ranebennur (43 Km) under phase II.
Engineering Procurement & Contract (EPC) Tender has been awarded on 17.02.2023 for the new line section between Koteganguru & Shikaripura (39.38 km) at a value of Rs. 454.18 Cr.
The work for the balance section is also planned to be executed through EPC mode of tendering after handing over of land by Government of Karnataka.