Hassan (Alur)-Belur (32 km)

PROGRESS OF WORKS FOR THE MONTH OF 
APRIL 2023

Cate-gory

Details of Work

Year of sanction

Anticipated /Sanctioned Cost

Cum. Exp. Up to March 2023

BG

2023-24

Exp. Up to the month/ Cum. Exp.

Physical progress

NLPB-19

Hassan (Alur) - Belur (32 km) 

2019-20

748.85

0.23 Cr.

30.00 Cr

(Cap.)

30.00(Dep)

 0.00/0.023

Nil

Remarks:-

Detailed estimate has been sanctioned for an amount of Rs.748.85 Cr on 30.09.2022. 

Land Survey by SLAO/Hassan is in progress in Belur Taluk.





Source : South Western Railway CMS Team Last Reviewed : 18-05-2023  


  SWR Personnel-Web Mail | Admin Login | Site Map | Contact Us | RTI | Disclaimer | Terms & Conditions | Privacy Policy Valid CSS! Valid XHTML 1.0 Strict

© 2016  All Rights Reserved.

This is the Portal of Indian Railways, developed with an objective to enable a single window access to information and services being provided by the various Indian Railways entities. The content in this Portal is the result of a collaborative effort of various Indian Railways Entities and Departments Maintained by CRIS, Ministry of Railways, Government of India.