PROGRESS OF WORKS FOR THE MONTH OF
APRIL 2023
Cate-gory | Details of Work | Year of sanction | Anticipated /Sanctioned Cost | Cum. Exp. Up to March 2023 | BG 2023-24 | Exp. Up to the month/ Cum. Exp. | Physical progress |
NLPB-19 | Hassan (Alur) - Belur (32 km) | 2019-20 | 748.85 | 0.23 Cr. | 30.00 Cr (Cap.) 30.00(Dep) | 0.00/0.023 | Nil |
Remarks:-
Detailed estimate has been sanctioned for an amount of Rs.748.85 Cr on 30.09.2022.
Land Survey by SLAO/Hassan is in progress in Belur Taluk.