PROGRESS OF WORKS FOR THE MONTH OF
FEBRUARY 2023
Cate-gory | Details of Work | Year of sanction | Anticipated /Sanctioned Cost | Cum. Exp. Up to March 2022 | BG for 2022-23 | Exp. Up to the month/ Cum. exp | Physical progress |
DLPB-24 | Hosadurga-Chickjajur(28.89) | | 297.99/203.40 | 297.23 | 2.00(Cap.) Rs.1000/-(EBR(IF)/IRFC) | 0.83/ 298.06 | 100% |
| | | | | | | | |
Remarks:-
Project completed and commissioned.