PROGRESS OF WORKS FOR THE MONTH OF
FEBRUARY 2023
Cate-gory | Details of Work | Year of sanction | Anticipated /Sanctioned Cost | Cum. Exp. Up to March 2022 | BG for 2022-23 | Exp. Up to the month/ Cum. exp | Physical progress |
DLPB-25 | Hospet -Hubli-Londa-Vasco-da-gama(352.58 Km) | 2010-11 | 3692.60 (100% Railway Funded) | 1430.47 | 100.00Cr.(Cap.) Rs.400Cr. (EBR/IF(IRFC)) | 174.18/ 1604.65 | 75.16% |
Remarks:-
This project is being executed by RVNL. So far 288.28 km has been commissioned.