PROGRESS OF WORKS FOR THE MONTH OF
FEBRUARY 2023
Cate-gory | Details of Work | Year of sanction | Anticipated /Sanctioned Cost | Cum. Exp. Up to March 2022 | BG for 2022-23 | Exp. Up to the month/ Cum. exp | Physical progress |
DL PB-27 | Hotgi-Kudgi-Gadag (284 km) | | 1877.81 (150 km-100% Rly 134 km-NTPC Funded) | 941.56(Rly:Kudgi-Gadag) 628.97(NTPC:Hotgi-Kudgi) | 10.00 (Cap.) 130.00 (EBR(IF)/IRFC)) 60.00 (Deposit) | 105.83/ 1047.39 8.66/ 637.63 (NTPC) | 70% |
Remarks:-
Doubling for part length of this project, i.e. from Hotgi - Kudgi (134 km) is taken up under Customer Funding Model. The section between Gadag to Kudgi (150 Km) is taken up as an EBR(IF) funded project.
The sections between Wandal - Hotgi (148 Km - NTPC Portion), Gadag - Hole Alur (52 Km) has been commissioned in phases between the Financial Years 2018 - 2022.
The section between and HoleAlur – Badami (19 Km) and Badami – Guledagudda (13.2 Km) has been commissioned in the current financial year 2022-23 on 02.12.2022 & 15.02.2023 respectively.
The balance section Guledagudda – Almatti (44 Km) is targeted to be commissioned in the FY 2023-24 and the section between Almatti – Wandal (08 Km) is targeted to be commissioned by December 2024.