Yelahanka-Penukonda

PROGRESS OF WORKS FOR THE MONTH OF
FEBRUARY 2023

 

Cate-gory

Details of Work

Year of sanction

Anticipated /Sanctioned Cost

Cum. Exp. Up to March 2022

BG for 2022-22

Exp. Up to the month/ Cum. exp

Physical progress

DL

PB-28

Yelahanka-Penukonda

(120.53 km)

2015-16

1200/860.43

1047.45

54.00 Cr

(Cap.)

104.55/ 1152.00

100%


Remarks:-

Entire Yelahanka - Penukonda Doubling was completed and commissioned on 29.03.2022 and dedicated to the nation by Hon’ble PM on 20.06.2022.





Source : South Western Railway CMS Team Last Reviewed : 18-04-2023  


  SWR Personnel-Web Mail | Admin Login | Site Map | Contact Us | RTI | Disclaimer | Terms & Conditions | Privacy Policy Valid CSS! Valid XHTML 1.0 Strict

© 2016  All Rights Reserved.

This is the Portal of Indian Railways, developed with an objective to enable a single window access to information and services being provided by the various Indian Railways entities. The content in this Portal is the result of a collaborative effort of various Indian Railways Entities and Departments Maintained by CRIS, Ministry of Railways, Government of India.