PROGRESS OF WORKS FOR THE MONTH OF
FEBRUARY 2023
Cate-gory | Details of Work | Year of sanction | Anticipated /Sanctioned Cost | Cum. Exp. Up to March 2022 | BG for 2022-22 | Exp. Up to the month/ Cum. exp | Physical progress |
DL PB-28 | Yelahanka-Penukonda (120.53 km) | 2015-16 | 1200/860.43 | 1047.45 | 54.00 Cr (Cap.) | 104.55/ 1152.00 | 100% |
Remarks:-
Entire Yelahanka - Penukonda Doubling was completed and commissioned on 29.03.2022 and dedicated to the nation by Hon’ble PM on 20.06.2022.