Miraj-Londa

PROGRESS OF WORKS FOR THE MONTH OF
FEBRUARY 2023

Cate-gory

Details of Work

Year of sanction

Anticipated /Sanctioned Cost

Cum. Exp. Up to March 2022

BE for 2022-23

Exp. Up to the month/ Cum. exp

Physical progress

DL PB-27 of C.Rly.

Miraj-Londa (185.90 km)

2015-16

1590.96

100% Railway Funded

1027.70

400.00

335.22/ 1362.92

 82%

Remarks:-

This project is part of Pune - Miraj - Londa Doubling (467 Km) sanctioned under Pink Book of Central Railway.

The sections between Ghataprabha - Kudachi (46 Km) has been commissioned in phases during 2019 - 2021.

The sections between Londa - Ghataprabha (108 Km) has been commissioned during the current Financial Year 2022 – 23. The same has been dedicated to the nation by Hon’ble Prime Minister of India on 27.02.2023.

The remaining section of Kudachi - Miraj (32 Km) is targeted to be commissioned in the Financial Year 2023 - 24.





Source : South Western Railway CMS Team Last Reviewed : 18-04-2023  


  SWR Personnel-Web Mail | Admin Login | Site Map | Contact Us | RTI | Disclaimer | Terms & Conditions | Privacy Policy Valid CSS! Valid XHTML 1.0 Strict

© 2016  All Rights Reserved.

This is the Portal of Indian Railways, developed with an objective to enable a single window access to information and services being provided by the various Indian Railways entities. The content in this Portal is the result of a collaborative effort of various Indian Railways Entities and Departments Maintained by CRIS, Ministry of Railways, Government of India.