PROGRESS OF WORKS FOR THE MONTH OF
FEBRUARY 2023
Cate-gory | Details of Work | Year of sanction | Anticipated /Sanctioned Cost | Cum. Exp. Up to March 2022 | BG for 2022-23 | Exp. Up to the month/ Cum. exp | Physical progress |
DLPB-33 | Penukonda - Dharmavaram (41.50 Km) | 2018-19 100% Railway funded | 308 Cr | 13.31 | Rs.10 Cr.(Cap.) Rs.50 Cr. (EBR-IF/IRFC) | 8.67/ 21.98 | 15% |
Remarks:
Engineering Procurement and Construction (EPC) tender has been awarded for the entire
stretch (41.5 Km) on 19.01.23 for a value of Rs. 266.66 Cr. The project is targeted to be
completed by October 2024 as per Vision 2024.