Sl. No | Details of Work | Year of sanction | | | Cum.Exp. Up to 30.06.2015 | Physical progress |
32 | Dharmavaram—Yelahanka Electrification (214 Km) as part of Gooty-Dharmavaram-Yelahanka Electrification project (304 Km) | 2010-11 | | | 176 Cr. (Total Rs.250.17 Cr for Gooty-Dhamaravaram-Yelahanka) | 85% |
Status: (i) Work being executed by RVNL. Erection of OHE Masts and wiring has been completed in the entire section from Yelahanka to Dharmavaram. (ii) Works of construction of Traction sub-station and switching stations is in progress.
Target:- March, 2016.
|
Sl. No | Details of Work | Year of sanction | | | Cum.Exp. Up to 30.06.2015 | Physical progress |
33 | Hospet-Bellary-Haddinagundu (92 km) as part of Hospet-Bellary-Guntakal Railway Electrification (138 km) | 2012-13 | | | - | - |
Ø Detailed Estimate at Rs.226.68 Cr for the entire Project (Rs.151 Cr from for section falling in SWR) was sanctioned in the year 2013. Project being executed by RVNL Status: Tenders are under evaluation and finalization. Project targeted for completion by March, 2018. |