1 | Water pipe line crossing | Maheshwarappa Chikkapattanagere - Kadur | SMET Sec. | 3 Km. btn Chikkapattanagere - Kadur | 15-07-2014 | Feasibility redceived from SSE/P.Way/SMET on 07.9.14. Letter to partyfor submission oftrenchless coston 17.9.14 | Party |
2 | Water pipe line crossing | Krishne Gowda S/O Late.Thimmegowda Hosagrahara , K.R. Nagar, Mysore | MYS | Km. NilHosaagrahar near Railway Station | 21.07.2014 | Feasibility for thesaid locationis notfeasibleas per SSE/P.Way/KRNR letter dated 07.10.2014.Hence, party has been advised on 09.10.2014 for submissionof alternative location. | Party |
3 | Water pipe line crossing | SannappaBevanahalli village MGF post | MYS | Km68/400-500 | 12.08.14 | Feasibility receivedfrom SSE/P. Way/KRNR on 07.10.2014. Party has been advised for submission of Land value and trenchless cost on 13.10.14 | Party |
4 | Water pipe line crossing | Nagaraju S/o Krishne Gowda K.R. Pet Taluk | MYS | Km.68/700-800 | 13.08.2014 | Feasibility for thesaid locationis notfeasibleas per SSE/P.Way/KRNR letter dated 07.10.2014.Hence, party has been advised on 09.10.2014 for submissionof alternative location. | Party |
5 | Water pipe line crossing | Vijyamma W/o late Shivarama Gowda, K.R. Pet | MYS | 54/700-800 | 22-08-2014 | Feasibility receivedfrom SSE/P. Way/KRNR on 07.10.2014. Party has been advised for submission of Land value and trenchless cost on 13.10.14 | Party |
6 | Water pipe line crossing | Shivarame Gowda S/oMallegowda, Bevinahalli Village MGF post,AKK Hobli | MYS | 68/800-900 | 22.08.2014 | Feasibility for thesaid locationis notfeasibleas per SSE/P.Way/KRNR letter dated 07.10.2014.Hence, party has been advised on 09.10.2014 for submissionof alternative location. | Party |
7 | OFC | The DivisionalEngineertelecom(BSNL) | TK-ASK | 81/500-600 | 25.8.2014 | Feasibility receivedfrom SSE/P. Way/TTR on 29.9.2014. Party has been advised on 13.10.14for submissionof trenchless cost & market value. | Party |
8 | OFC | The DivisionalEngineertelecom(BSNL) | TK-ASK | 139/900-140/00 | 27.8.14 | Feasibility receivedfrom SSE/P. Way/TTR on 01.09.2014. Party has been advised on 13.10.14 for submission oftrenchless cost & market value. | Party |
9 | UGDpipe line crossing | AEE.KUWS & D.B. Sub Divsion Hassan | ASK | 166/800-900 | 1.9.2014 | Feasibility for thesaid locationis notfeasibleas per SSE/P.Way/ASK letter dated 07.10.2014.Hence, party has been advised on 10.10.2014 for submissionof alternative location. | Party |
10 | UGDpipe line crossing | AEE.KUWS & D.B. Sub Divsion Hassan | ASK | 164/900-165/000 | 1.9.2014 | Feasibility receivedfrom SSE/P. Way/ASK on08.10.2014. Estimate under preparation | |
11 | UGDpipe line crossing | AEE.KUWS & D.B. Sub Divsion Hassan | ASK | 164/700-800 | 1.9.2014 | Feasibility for thesaid locationis notfeasibleas per SSE/P.Way/ASK letter dated 06.10.2014.Hence, party has been advised on 10.10.2014 for submissionof alternative location. | Party |
12 | Water pipe line crossing | Lakshme Gowds H.S. S/o subbegowda No.88 Taponidhi Arkavathi Road Crossinglayout Mysore | MYS | 69/100-69/400 | 1.9.2014 | Feasibility for thesaid locationis notfeasibleas per SSE/P.Way/KRNR letter dated 07.10.2014.Hence, party has been advised on 09.10.2014 for submissionof alternative location. | Party |
13 | Water pipe line crossing | Indrama W/O Javarappagowda, Alenahalli Village & Post. AKK Hobli, K.R.Pet | MYS | 64/100-200 | 15.9.2014(28.08.2014) | Feasibility for thesaid locationis notfeasibleas per SSE/P.Way/KRNR letter dated 07.10.2014.Hence, party has been advised on 09.10.2014 for submissionof alternative location. | Party |
14 | TV Cable | yapura Gone Gowda S/oHanumanthappa , Ballary | RNR | 362/8-9 | 18.9.2014 | Feasibility receivedfrom SSE/P. Way/RNR on29.9.14. Acceptance letter called fromparty for change of location on7.10.2014 | Party |
15 | UGD pipe line crossing | CommissionerCity Corporation Davanagere | DVG | Km 319.9 | 22.9.14 | Feasibility calledfrom SSE/P. Way/DVG on25.9.14 | |
16 | UGD pipe line crossing | CommissionerCity Corporation Davanagere | DVG | Km 321.6 | 22.9.14 | Feasibility calledfrom SSE/P. Way/DVG on25.9.14 | |
17 | Water pipe line crossing | Venkate Gowda S/oAppe Gowda Alenahalli AkkiheballaK.R. Pet | MFG-KRNR | 63/700-800 | 26.9.14 | Feasibility calledfrom SSE/P. Way/KRNR on26.9.14 | |
18 | Water pipe line crossing | Dayananda P.G. S/o late Gangadaraiah ,Pura, Nittur Hobli &Post Gubbi Taluk, Tumkur. | ASK Sec | 95/00-100GBB-NTR | 13.9.14 | Feasibility calledfrom SSE/P. Way/TTR on19.9.14 | |
19 | Water pipe line crossing | M.K. RavilaS/o Kalegowda, Mandagere village, Akkihebbal (Hobli), K.R.Pet Taluk, Mandya Dist.. | MYS Sec | 67/100-200MYS-ASK | 25.8.14 | Feasibility calledfrom SSE/P. Way/KRNR on25.8.14 | |
20 | Water pipe line crossing | Mohan N.K. S/o lateKala shetty Mandagere village, Akkihebbal (Hobli), K.R.Pet Taluk, Mandya Dist. | MYS Sec | 68/300-400 MGF station | 14.10.14 | Feasibility calledfrom SSE/P. Way/KRNR on14.10.14 | |
21 | Water pipe line crossing | Bhoje gowada G.V. S/o VenkategowdaGaddehosur villegeMandagere post, Akkihebbal (Hobli), K.R.Pet Taluk, Mandya Dist. | MYS Sec | 66/000-66/100 or 65/900-66/000KRNR-MGF station | 15.10.14 | Feasibility calledfrom SSE/P. Way/KRNR on15.10.14 | |
22 | Water pipe line crossing | Shivannagowada G.S. S/o SannappagowdaGaddehosur villegeMandagere post, Akkihebbal (Hobli), K.R.Pet Taluk, Mandya Dist. | MYS Sec | 65/200-300KRNR-MGF station | 15.10.14 | Feasibility calledfrom SSE/P. Way/KRNR on15.10.14 | |
23 | OFC | Divisional Engg TelecomOFC porject, Micro wave stations H.N. Pura road, Hassan. | MYS Sec | Over BridgeHAS-CNPA Railway line | 14.10.2014 | Feasibility& Market value calledfrom SSE/P. Way/HAS on16.10.14 | |