Targets for Commissioning of Doubling & New Lines for 2021-22 |
SN | Name of the Project | Section Targeted 21-22 | CE In-charge (CN) | Length (Km) | TDC (Revised) &Pending with Board | Status of work |
DOUBLING |
1 | Yelahanka - Penukonda (120.53 Km) | Devarappalli - Hindupur | CE/Plg | 10 | Nov - 21 | • Finishing works are in progress |
Hindupur - Penukonda | CE/West | 38 | Dec - 21 | • Track linking work is in progress. |
2 | Londa - Miraj (186 Km) | Khanapur - Belagavi | CE/II/UBL | 26 | Feb - 22 | • Track linking work is in progress. |
Belaghavi - Suldhal | CE/II/UBL | 27 | Feb - 22 | • Earthwork and bridge works are in final stage • Track linking work is in progress |
Londa - Khanapur | CE/II/UBL | 25 | Mar - 22 | • Track linking work is in progress. |
3 | Hotgi-Kudgi-Gadag (284 Km) | Hombal - Hole Alur | CE/I/UBL | 36 | Nov - 21 | Finishing works are in progress |
Gadag - Hombal | CE/I/UBL | 16 | Jan - 22 | • Track linking work is in progress. |
4 | Arsikere - Tumkur (96 Km) | Nittur - Banasandra | CE/East | 22 | Jan - 22 | • Track linking work is in progress. |
5 | Hubli - Chikjajur (190 Km) | Yalvigi - Saunshi | CE/I/UBL | 23 | Jan - 22 | • Earthwork and bridge works are in final stage • Track linking work is in progress |
Haveri - Savanur | CE/North | 20 | Feb - 22 | • Track linking work yet to start |
Savanur - Yalvigi | CE/I/UBL | 7 | Feb - 22 | • Track linking work yet to start |
TOTAL FOR (SWR) | 250 |
NEW LINE |
1 | Gadag - Wadi (252 Km)
| Talkal - Sangnal | CE/South | 22 | Mar - 22 | • Track linking work is in progress. |
TOTAL | 22 |
GRAND TOTAL SWR | 272 |
|
Targets for Commissioning of Doubling & New Lines for 2021-22 |
SN | Name of the Project | Section Targeted 21-22 | CE In- charge (CN) | Length (Km) | TDC (Revised) &Pending with Board | Status of work |
DOUBLING |
1 | Hotgi-Kudgi-Gadag (284 Km) | Badami-Bagalkot
| CE/I/UBL | 26 | Jan 23 | • Earthwork and Trucking out of P.way materials are in progress |
Hole Alur - Badami | CE/I/UBL | 19 | Oct 22 | • Bridge works and Earthwork is in progress |
2 | Hubli - Chikjajur (190 Km) | Hubli South - Saunshi | CE/I/UBL | 20 | Dec 22 | • Bridge works, Earthwork and Blanketting works are in progress |
Devargudda - Haveri | CE/North | 25 | Dec 22 | • Bridge works, Earthwork and Blanketting works are in progress |
3 | Londa-Miraj (186 km) | Suldhal-Ghataprabha | CE/II/UBL | 30 | Dec 22 | • Work in progress |
Kudachi-Miraj | CE/II/UBL | 32 | Feb 23 | • Work in progress |
4 | BANGALORE – Whitefield – Bangalore City - Krishnarajapuram Quadrupling (38 Km) | Bangalore Cantonment - Baiyappanahalli
| CE/West | 13 | Dec 22 | • Work in progress |
TOTAL FOR (SWR) | 165 |
NEW LINE |
1 | Ginigera - Raichur (165 Km)
| Karatagi - Sindhanur | CE/South | 18.5 | Jun - 22 | • Bridge works and Earthwork is in progress |
2 | Rayadurg-Tumkur (207 Km) | Kadiridevarapalli-Doddahalli | CE/East | 20 | Feb - 23 | • Land acquistion is in progress |
Tumkur - Urukere | CE/East | 11 | • Land acquistion is in progress |
3 | Gadag-Wadi (257 Km)
| Sangnal - Kushtagi | CE/South | 34 | Jan - 23 | • Work in progress |
4 | Tumkur – Chitradurg – Davangere (191 Km)
| Urukere - Timmarajanahalli | CE/North | 13 | Feb - 23 | • Land acquistion is in progress |
TOTAL | 96.5 |
GRAND TOTAL SWR | 261.5 |