Screen Reader Access Skip to Main Content Font Size   Increase Font size Normal Font Decrease Font size
Indian Railway main logo
Search :
View Content in Hindi
National Emblem of India

About Us

News & Recruitment

Tenders

Construction Projects

Commercial ,Freight Information & Public Information

For IR Personnel

Contact Us



 
Bookmark Mail this page Print this page
QUICK LINKS
Rayadurga-Tumkur

PROGRESS OF WORKS FOR THE MONTH OF
DECEMBER 2022

Cate-gory

Details of Work

Year of sanction

Anticipated /Sanctioned Cost

Cum. Exp. Up to March 2022

BG

2022-23

Exp. Up to the month/ Cum. Exp.

Physical progress

NLPB-6

Rayadurga-Tumkur(207Km)(12 Block sections)

2007-08

2404.03

on 50:50 cost sharing basis between Rly and Gok / GoAP

1098.72

50 Cr(Cap.)

50 Cr(Deposit)

 

38.94/ 1137.66

58%

Remarks:-

 

Section from Rayadurga-Kalyanadurga-Kadiridevarapalli (63 km) which falls in A.P. was commissioned in 2016-17. 


     Section between Kadiridevarapalli - Doddahalli (20 km) is targeted for the current financial year 2022 - 23.

  The work for the remaining sections is planned to be taken up under Engineering Procurement & Construction mode of tendering after handing over of 90 % of land by Government of Karnataka. EPC Tender called for section between Tumkur-Koratagere (30 km) for a value of Rs.270.31 Cr on 16.11.2022 and is due for opening on 16.01.2023.





 




Source : South Western Railway CMS Team Last Reviewed : 12-01-2023  


  SWR Personnel-Web Mail | Admin Login | Site Map | Contact Us | RTI | Disclaimer | Terms & Conditions | Privacy Policy Valid CSS! Valid XHTML 1.0 Strict

© 2016  All Rights Reserved.

This is the Portal of Indian Railways, developed with an objective to enable a single window access to information and services being provided by the various Indian Railways entities. The content in this Portal is the result of a collaborative effort of various Indian Railways Entities and Departments Maintained by CRIS, Ministry of Railways, Government of India.