PROGRESS OF WORKS FOR THE MONTH OF
DECEMBER 2022
Cate-gory | Details of Work | Year of sanction | | Cum. Exp. Up to March 2022 | BG 2022-23 | Exp. Up to the month/ Cum. Exp. | Physical progress |
NLPB-3 SC Rly | Munirabad (Ginigera)-Raichur(165 km) | 2007-08 | 2599.67/1350.91 Cost sharing on 50: 50 basis between GoK &Rly. | 1423.00 | 100 Cr(Cap.) 100 Cr (Deposit) | 94.65/ 1517.65 | 60% |
Remarks:- Section between Ginigera-Chikkabenakal (27 km) commissioned on 31.03.2017 for passenger traffic. Chikkabenakal - Gangavathi – 13 km commissioned on 04.03.2019. Gangavathi - Karatagi (26 km) commissioned on 31.05.2022. The section between Karatagi - Sindhanur (18.5 km) is targeted to be commissioned in the current financial year 2022-23. The work in the balance section is planned to be taken up under Engineering Procurement & Construction mode of tendering after handing over of 90% land by Government of Karnataka. | |