PROGRESS OF WORKS FOR THE MONTH OF
July 2020
Cate-gory | Details of Work | Year of sanction | | Cum. Exp. Up to March 2020 | RG for 2020-21 | Exp. Up to the month/ Cum. Exp. | Physical progress |
NLPB-3 SC Rly | Munirabad (Ginigera)-Raichur(165 km) | 2007-08 | 1350.91 Cost sharing on 50: 50 basis between GoK &Rly. | 1148.78 | 60.00 | 90.61/ 1284.41 | 40% |
Remarks:- Section between Ginigera-Chikkabenakal (27 km) commissioned on 31.03.2017 for passenger traffic. Chikkabenakal (Km 27)-Gangavathi (Km 40) – 13 km commissioned on 04.03.2019. Gangavathi (km 40)-Karatagi (Km 68)-Sidhanur (km 84) - CRS inspection done on 30.05.2020 and authorization received. | |