PROGRESS OF WORKS FOR THE MONTH OF
July 2020
Cate-gory | Details of Work | Year of sanction | | Cum. Exp. Up to March 2020 | BG for 2020-21 | Exp. Up tothe month/ Cum. Exp. | Physical progress |
NL PB-5 | Hejjala-Chamarajanagar (142 km) (part of Bangalore-Satyamangalam(260 kms) | 1996-97 | 1382.78 on 50:50 cost sharing basis & land free of cost by GOK for Hejjala to Chamarajanagar | 7.35 | 0.00 | 0.00/ 7.35 | Nil |
Remarks:- Originally the project was sanctioned between Bangalore-Satyamangalam (260 km). Permission was not granted by Tamilnadu Government as well as CEC to carry out survey in the Satyamangalam Forest Area.Hence project is now being taken up from Hejjala to Chamarajnagar (142 Kms).Land yet to be given by State Govt.
1. Project kept under “ABEYANCE” vide Railway Board letter dated 23.10.2019. | |