PROGRESS OF WORKS FOR THE MONTH OF
APRIL 2023
Cate-gory | Details of Work | Year of sanction | Anticipated /Sanctioned Cost | Cum. Exp. Up to March 2023 | BG for 2023-24 | Exp. Up to the month/ Cum. exp | Physical progress |
NL PB-13 | Gadag-Wadi (257 km) | 2013-14 | 2841.84 with cost sharing basis & land free of cost by GOK | 627.84 Cr | 200 Cr.(SF.) 150 Cr. (Deposit) | 29.49/657.33 | 22 |
Remarks: -
The section between Talkal - Sangnal (22 kms) has been commissioned in March 2022.
The section between Sangnal - Linganbandi (23.7 km) is targeted to be commissioned in March 2023 and the section between Linganbandi - Kushtagi (10 km) is targeted to be commissioned in the Financial Year 2023-24.
Engineering Procurement & Construction (EPC) tender has been floated for the section between Kushtagi – Jumlapur Road (20 Km) and is opening on 14.04.2023.
The work for the balance sections is planned to be taken up in phases through EPC mode of tendering after handing over of 90% of land by Government of Karnataka.