PROGRESS OF WORKS FOR THE MONTH OF
July 2020
Cate-gory | Details of Work | | Anticipated /Sanctioned Cost | Cum. Exp. Up to March 2020 | BG for 2020-21 | Exp. Up to the month/ Cum. exp | Physical progress |
NL PB-13 | Gadag-Wadi (252 km) | | 2841.84 with cost sharing basis & land free of cost by GOK | 207.87 | 60.00 | 57.50/ 265.39 | Nil |
Remarks:- State Govt. has decided to acquire land through KIADB for this project.
Work commenced between Talkal-Kushtagi (57 km), where 1877 acres of land has been handed over to Railway by State Govt. Between Shahpur-Wadi (47 km), out of total requirement of 662 Ac of land, 646 Ac is handed over to Railways. |