PROGRESS OF WORKS FOR THE MONTH OF
FEBRUARY 2023
Cate-gory | Details of Work | Year of sanction | Anticipated /Sanctioned Cost | Cum. Exp. Up to March 2022 | BG for 2022-23 | Exp. Up to the month/ Cum. exp | Physical progress |
NL | Kolar-Mulbagal-Madaghatta NL (50.52 km) | 2008-09 | 782.57 | 0.66 | 0.0001 Cr (Cap.) 289 Cr (Deposit) | 0.00/ 0.66 | Nil |
Remarks :-
The New BG Line between Kolar - Mulbagal has been sanctioned as a Material
Modification to Cuddappah - Bangalore New Line project (260 Km) executed by South
Central Railways.
SWR was asked by Railway Board to also execute Mulbagal - Madaghatta portion.
Accordingly a combined estimate was sanctioned for Kolar - Madaghatta.
Govt. Of AP vide Hon’ble Chief Minister letter dated 17.06.2021 has requested for the
change of alignment of this project to Kadapa-Muddanuru-Pulivendula-Muddiguba - Sri
Satya Sai Prashanthi Nilayam – Bangalore.
In view of the above, no work is being executed in South Cenral Railways in Kadapa –
Madagatta section.
SWR is waiting for the final outcome of the sanctioned work of Kadapa - Madagatta - Mulbagal - Bengaluru.