PROGRESS OF WORKS FOR THE MONTH OF
DECEMBER 2022
Cate-gory | Details of Work | Year of sanction | | Cum. Exp. Up to March 2022 | BG for 2022-23 | Exp. Up to the month/ Cum. Exp. | Physical progress |
NLPB-7 | Bagalkot-Kudachi(142 kms) | 2010-11 | 1654.65/1378 on 50:50 cost sharing basis & land free of cost by GOK | 326.63 | 25.00(Cap.) 25.00(Deposit) | 9.46/ 336.09 | 30% |
CRS inspection between Bagalkot-Khajdoni (30 km) done on 14.06.2017 and commissioned on 21.06.2018. Kajjidoni - Lokapur - Land acquisition 100% completed. Tender awarded and work is in progress.EPC Tender called for section between Lokapur - Yadwad (21 Km) on 15.11.2022 for a value of Rs.357.45 Cr and is due for opening on 20.02.2023.From Yadwad (Km 58/900) to Kudachi (Km142/000) land is yet to be handed over to the Railway from GoK |