PROGRESS OF WORKS FOR THE MONTH OF
July 2020
Cate-gory | Details of Work | Year of sanction | | Cum. Exp. Up to March 2020 | BG for 2020-21 | Exp. Up to the month/ Cum. Exp. | Physical progress |
NLPB-7 | Bagalkot-Kudachi(142 kms) | 2010-11 | 986.30 on 50:50 cost sharing basis & land free of cost by GOK | 305.06 | 15.00 | 1.07/ 317.63 | 22% |
CRS inspection between Bagalkot-Khajdoni (30 km) done on 14.06.2017 and authorisation received. Further work beyond Khajdoni can be taken up on acquisition of land by State Govt. |