Cate-gory | Details of Work | Year of sanction | | Cum. Exp. Up to March 2022 | BG for 2022-23 | Exp. Up to the month/ Cum. Exp. | Physical progress | NL PB-1 | Kottur-Harihar (65kms) | 1995-96 | 488.70 Cost sharing 2/3: 1/3 between GoK & Rly | 442.07 | 0.0001Cr.(Cap.) 68 Cr(Deposit) | 1.29/ 443.36 | 100% | Remarks: - Section completed and commissioned (65 Kms) on 03.03.2014 on “One Train System only”.Section is commissioned on “Absolute Block System” of working on 30.05.2016. |
Source : South Western Railway CMS Team Last Reviewed : 12-01-2023
|
|
|