Malgur - Palasamudram

PROGRESS OF WORKS FOR THE MONTH OF
APRIL 2023

Cate-gory

Details of Work

Year of sanction

Anticipated /Sanctioned Cost

Cum. Exp. Up to March 2023

BG for 2023-24

Exp. Up to the month/ Cum. Exp.

Physical progress

NL

PB-21

Malgur - Palasamudram (17.975 km)

2022-23

323.14

100% railway funded

0.00

20.00

0.032/0.032

Nil

Railway Board has sanctioned New line between Malugur - Palasamudram (17.975 km) for an amount of Rs.323.14 Cr vide Railway Board letter No. 2022/W-1/NL/SWR/MLU-PALA dtd.09.09.2022.

Engineering Procurement and Construction (EPC) Tender has been floated for the entire stretch with bid opening date on 17.04.2023.





Source : South Western Railway CMS Team Last Reviewed : 18-05-2023  


  SWR Personnel-Web Mail | Admin Login | Site Map | Contact Us | RTI | Disclaimer | Terms & Conditions | Privacy Policy Valid CSS! Valid XHTML 1.0 Strict

© 2016  All Rights Reserved.

This is the Portal of Indian Railways, developed with an objective to enable a single window access to information and services being provided by the various Indian Railways entities. The content in this Portal is the result of a collaborative effort of various Indian Railways Entities and Departments Maintained by CRIS, Ministry of Railways, Government of India.