PROGRESS OF WORKS FOR THE MONTH OF
APRIL 2023
Cate-gory | Details of Work | Year of sanction | Anticipated /Sanctioned Cost | Cum. Exp. Up to March 2023 | BG for 2023-24 | Exp. Up to the month/ Cum. Exp. | Physical progress |
NL PB-21 | Malgur - Palasamudram (17.975 km) | 2022-23 | 323.14 100% railway funded | 0.00 | 20.00 | 0.032/0.032 | Nil |
Railway Board has sanctioned New line between Malugur - Palasamudram (17.975 km) for an amount of Rs.323.14 Cr vide Railway Board letter No. 2022/W-1/NL/SWR/MLU-PALA dtd.09.09.2022.
Engineering Procurement and Construction (EPC) Tender has been floated for the entire stretch with bid opening date on 17.04.2023.