Ramanagaram-Mysore

Cate-gory

Details of Work

Year of sanction

Anticipated /Sanctioned Cost

Cum. Exp. Up to March 2022

BG for 2022-23

Exp. Up to the month/ Cum. exp

Physical progress

DLPB-23

Ramanagaram - Mysore doubling (94km) with electrification of Kengeri-Mysore

2007-08

1200/874.57

50:50

(Rly:GoK)

1143.62

20.00

(EBR(IF)/IRFC)

31.87/1175.49

95%

Remarks:-

Entire doubling between Ramanagaram-Mysore (94 km) along with electrification has been completed and commissioned in Nov.2017.  With this the entire doubling work between Bangalore to Mysore has been completed and commissioned. The electrification between Bangalore - Mysore was dedicated to the Nation by Hon'ble Prime Minister on 19.02.2018 at Mysore.




Source : South Western Railway CMS Team Last Reviewed : 12-01-2023  


  SWR Personnel-Web Mail | Admin Login | Site Map | Contact Us | RTI | Disclaimer | Terms & Conditions | Privacy Policy Valid CSS! Valid XHTML 1.0 Strict

© 2016  All Rights Reserved.

This is the Portal of Indian Railways, developed with an objective to enable a single window access to information and services being provided by the various Indian Railways entities. The content in this Portal is the result of a collaborative effort of various Indian Railways Entities and Departments Maintained by CRIS, Ministry of Railways, Government of India.