Cate-gory | Details of Work | | Anticipated /Sanctioned Cost | Cum. Exp. Up to March 2020 | B for 2020-21 | Exp. Up to the month/ Cum. exp | Physical progress | DL PB-36 | Yelahanka-Penukonda (120.55 km) | | 988.37 | 822.49 | 155.00 | 33.68/ 856.17 | 25% | Remarks:- 1. A portion of this project, i.e. 48.2 km falls in A.P. out of total length of 120.53 km. 2. Makalidurga-Devarapalli (36 km) commissioned on 05.04.2019. Work is in progress between Yelahanka-Doddaballapur-Makalidurga (36 km). |
Source : South Western Railway CMS Team Last Reviewed : 19-08-2020
|
|
|