PROGRESS OF WORKS FOR THE MONTH OF
MARCH 2023
Cate-gory | Details of Work | Year of sanction | Anticipated /Sanctioned Cost | Cum. Exp. Up to March 2022 | BG for 2022-23 | Exp. Up to the month/ Cum. exp (Feb 23) | Physical progress |
DL PB-29 | Hubli-Chikjajur (190 km) | 2015-16 | 1849.50/1156.94 100% Rly funded | 1338.12 | 10.00 | 184.85/ 1522.97 | 100% |
Remarks :-
Sections between Chikjajur - Devaragudda, Haveri - Saunshi & Hubli - Hubli South (Total 145 km) has been commissioned in phases during 2018 - 2022.
Balance sections Hubli South - Saunshi (20 Km) & Devaragudda - Haveri (25 Km) has been commissioned in the Financial Year 2022-23 on 11.01.2023 and 15.03.2023 respectively.
With this the entire project has been completed and commissioned.