Hubli-Chikjajur

PROGRESS OF WORKS FOR THE MONTH OF
MARCH 2023

Cate-gory

Details of Work

Year of sanction

Anticipated /Sanctioned Cost

Cum. Exp. Up to March 2022

BG for 2022-23

Exp. Up to the month/ Cum. exp

(Feb 23)

Physical progress

DL

PB-29

Hubli-Chikjajur (190 km)

2015-16

1849.50/1156.94

100% Rly funded

1338.12

10.00

184.85/

1522.97

100%

Remarks :-

Sections between Chikjajur - Devaragudda, Haveri - Saunshi & Hubli - Hubli South (Total 145 km) has been commissioned in phases during 2018 - 2022.

Balance sections Hubli South - Saunshi (20 Km) & Devaragudda - Haveri (25 Km) has been commissioned in the Financial Year 2022-23 on 11.01.2023 and 15.03.2023 respectively.

With this the entire project has been completed and commissioned.





Source : South Western Railway CMS Team Last Reviewed : 18-04-2023  


  SWR Personnel-Web Mail | Admin Login | Site Map | Contact Us | RTI | Disclaimer | Terms & Conditions | Privacy Policy Valid CSS! Valid XHTML 1.0 Strict

© 2016  All Rights Reserved.

This is the Portal of Indian Railways, developed with an objective to enable a single window access to information and services being provided by the various Indian Railways entities. The content in this Portal is the result of a collaborative effort of various Indian Railways Entities and Departments Maintained by CRIS, Ministry of Railways, Government of India.