Sl. No | Cate-gory | Details of Work | Year of sanction | | | Cum.Exp. Up to 31.03.17 | Physical progress | 1 | DL PB-32 | Shivani-Hosadurga (10 kms) | | 33.36 | 60.00 (approx.) | 62.48 | 100% | - The entire Shivani-Hosadurga DL project has been completed and commissioned in Feb.2015
and section handed over to open line on 06.04.2015.