Yelahanka-Penukonda

Sl. No

Cate-gory

Details of Work

Year of sanction

Original sanctioned Pink Book cost

Latest Anticipated /Sanctioned Cost

Cum.Exp. Up to 31.03.17

Physical progress

11

DL

PB-35

Yelahanka-Penukonda (120.55 km)

2015-16

958.00

860.43

215.41

-

1.   The doubling project has been sanctioned by Railway Board as per Pink book item No.35 of 2015-16 with allocation as EBR (IF). 

2.   Govt. of Andhra Pradesh communicated their consent for sharing 50% of the cost for the stretch (48.2 km) that falls in A.P. out of total length of 120.53 km.

3.   In principle approval of ‘Niti Ayog’ communicated by Railway Board vide letter dated 14.08.2015 and tenders invited as per Railway Board’s letter dated 03.08.2015. Final sanction for the project  has been communicated by Railway Board vide their letter dated 18.11.2015.

4.   All contracts of earthwork and minor bridges (4 nos.) have been awarded and work is also in progress.  The project is planned to be commissioned in 4 years, i.e. by 2019-20.





Source : दक्षिण पश्चिम रेलवे CMS Team Last Reviewed : 26-07-2023  


  प्रशासनिक लॉगिन | साईट मैप | हमसे संपर्क करें | आरटीआई | अस्वीकरण | नियम एवं शर्तें | गोपनीयता नीति Valid CSS! Valid XHTML 1.0 Strict

© 2010  सभी अधिकार सुरक्षित

यह भारतीय रेल के पोर्टल, एक के लिए एक एकल खिड़की सूचना और सेवाओं के लिए उपयोग की जा रही विभिन्न भारतीय रेल संस्थाओं द्वारा प्रदान के उद्देश्य से विकसित की है. इस पोर्टल में सामग्री विभिन्न भारतीय रेल संस्थाओं और विभागों क्रिस, रेल मंत्रालय, भारत सरकार द्वारा बनाए रखा का एक सहयोगात्मक प्रयास का परिणाम है.