Arsikere-Tumkur

Sl. No

Cate-gory

Details of Work

Year of sanction

Original sanctioned Pink Book cost

Latest Anticipated /Sanctioned Cost

Cum.Exp. Up to  31.03.17

Physical progress

12

DL

PB-37

Arsikere-Tumkur (96km)

2015-16

960.00

578.00

248.20

-

1.   The doubling project has been sanctioned by Railway Board as per Pink book item No.37 of 2015-16. 

2.    In principle approval of ‘Niti Ayog’ received from Railway Board letter dt. 14.08.2015. 

3.   Contracts for earthwork, minor bridges, major bridges, construction of platforms and S&T accommodation, etc. for entire stretch of 96 km between Arsikere-Tumkur have been awarded and the work has commenced. 

4.     Physical work has already commenced for the project which is planned to be commenced in 3 years, i.e. by 2019-20.




Source : दक्षिण पश्चिम रेलवे CMS Team Last Reviewed : 26-07-2023  


  प्रशासनिक लॉगिन | साईट मैप | हमसे संपर्क करें | आरटीआई | अस्वीकरण | नियम एवं शर्तें | गोपनीयता नीति Valid CSS! Valid XHTML 1.0 Strict

© 2010  सभी अधिकार सुरक्षित

यह भारतीय रेल के पोर्टल, एक के लिए एक एकल खिड़की सूचना और सेवाओं के लिए उपयोग की जा रही विभिन्न भारतीय रेल संस्थाओं द्वारा प्रदान के उद्देश्य से विकसित की है. इस पोर्टल में सामग्री विभिन्न भारतीय रेल संस्थाओं और विभागों क्रिस, रेल मंत्रालय, भारत सरकार द्वारा बनाए रखा का एक सहयोगात्मक प्रयास का परिणाम है.